Lean Six Sigma Black Belt Six Sigma & Lean Foundations – MCQs
Questions across 5 chapters of Lean Six Sigma Black Belt Six Sigma & Lean Foundations. Pick a chapter, read sample questions with answers, then take a free test. Available in English.
📚 Chapters
✅ Practice questions with answers
Six Sigma was first developed as a methodology at:
Six Sigma Fundamentals & Metrics
- Toyota
- Ford
- Motorola
- General Electric
Show answer
Answer: C — Motorola
Bill Smith at Motorola in the mid-1980s.
How to solve:Six Sigma reduces variation and defects using DMAIC. 6 sigma (with 1.5 sigma shift) = 3.4 DPMO. DPMO = defects / (units x opportunities) x 1,000,000. RTY = product of each step's first-pass yield.
The main purpose of the Define phase is to:
Define Phase: Charter, VOC & CTQ
- implement solutions
- clearly define the problem, customer requirements, scope and goals
- set control charts
- collect all data
Show answer
Answer: B — clearly define the problem, customer requirements, scope and goals
Define phase.
How to solve:Define: project charter (problem, goal, scope, business case, team, timeline), VOC to CTQ, SIPOC, stakeholder analysis. Goals should be SMART.
The five Lean principles (Womack and Jones) are:
- value, value stream, flow, pull and perfection
- define, measure, analyze, improve, control
- sort, set, shine, standardise, sustain
- plan, do, check, act, repeat
Show answer
Answer: A — value, value stream, flow, pull and perfection
Lean Thinking.
How to solve:Lean: value as defined by the customer, value stream, flow, pull, perfection. 8 wastes = DOWNTIME (Defects, Overproduction, Waiting, Non-utilised talent, Transportation, Inventory, Motion, Extra-processing). Takt = available time / demand.
The 7 basic quality tools were popularised by:
- Henry Ford
- Taiichi Ohno
- Jack Welch
- Kaoru Ishikawa
Show answer
Answer: D — Kaoru Ishikawa
Ishikawa's tools.
How to solve:7 basic tools: check sheet, Pareto chart, cause-and-effect (fishbone), histogram, scatter diagram, control chart, flowchart/stratification. Pareto 80/20 rule. Fishbone 6Ms.
The main purpose of the Measure phase is to:
Measure Phase: Data & Sampling
- choose the solution
- close the project
- establish baseline performance and ensure data is reliable
- implement solutions
Show answer
Answer: C — establish baseline performance and ensure data is reliable
Measure phase.
How to solve:Data types: continuous (variable) vs discrete (attribute). Scales: nominal, ordinal, interval, ratio. Sampling: random, stratified, systematic, cluster. Operational definitions make measurement consistent.
The CEO most associated with popularising Six Sigma at GE in the 1990s was:
Six Sigma Fundamentals & Metrics
- Henry Ford
- Jack Welch
- W. Edwards Deming
- Taiichi Ohno
Show answer
Answer: B — Jack Welch
GE made Six Sigma famous.
How to solve:Six Sigma reduces variation and defects using DMAIC. 6 sigma (with 1.5 sigma shift) = 3.4 DPMO. DPMO = defects / (units x opportunities) x 1,000,000. RTY = product of each step's first-pass yield.
A project charter typically includes:
Define Phase: Charter, VOC & CTQ
- problem statement, goal statement, business case, scope, team and timeline
- only the budget
- only the solution
- the final results
Show answer
Answer: A — problem statement, goal statement, business case, scope, team and timeline
Charter content.
How to solve:Define: project charter (problem, goal, scope, business case, team, timeline), VOC to CTQ, SIPOC, stakeholder analysis. Goals should be SMART.
The acronym DOWNTIME for the 8 wastes includes:
- none of these wastes
- Design, Output, Work, Need, Time, Input, Money, Effort
- Delay, Order, Weight, Noise, Tax, Idle, Mess, Error
- Defects, Overproduction, Waiting, Non-utilised talent, Transportation, Inventory, Motion, Extra-processing
Show answer
Answer: D — Defects, Overproduction, Waiting, Non-utilised talent, Transportation, Inventory, Motion, Extra-processing
8 wastes.
How to solve:Lean: value as defined by the customer, value stream, flow, pull, perfection. 8 wastes = DOWNTIME (Defects, Overproduction, Waiting, Non-utilised talent, Transportation, Inventory, Motion, Extra-processing). Takt = available time / demand.
A Pareto chart is used to:
- calculate Cpk
- show trends over time
- identify the vital few causes that contribute most to a problem
- test hypotheses
Show answer
Answer: C — identify the vital few causes that contribute most to a problem
80/20 rule.
How to solve:7 basic tools: check sheet, Pareto chart, cause-and-effect (fishbone), histogram, scatter diagram, control chart, flowchart/stratification. Pareto 80/20 rule. Fishbone 6Ms.
Continuous (variable) data is:
Measure Phase: Data & Sampling
- colours
- measured on a scale that can take any value within a range, such as time or weight
- counted categories only
- yes/no only
Show answer
Answer: B — measured on a scale that can take any value within a range, such as time or weight
Variable data.
How to solve:Data types: continuous (variable) vs discrete (attribute). Scales: nominal, ordinal, interval, ratio. Sampling: random, stratified, systematic, cluster. Operational definitions make measurement consistent.
💡 How to practise
- Read each rule (UCP 600, ISBP, URDG, ISP98) article by article and practise the matching chapter.
- Case-scenario questions test how rules work together — review every explanation.
- Take a timed exam to get used to answering under pressure.
- Repeat chapters where you score below 75%.